Board forming and stripping For wall footings, grade beams, column footings, site curbs and steps. Includes 5% waste. Per SF of contact area. When forms are required on both sides of the concrete, include the contact surface for each side.
2" thick forms and bracing, using 2.85 BF of form lumber per SF. Includes nails, ties, and form oil [view picture]
  Using 2" lumber, per MBF — MBF 611.00 — 611.00
  Using nails, ties and form oil, per SF — SF .22 — .22
  1 use B2@.115 SF 2.03 3.96 5.99
  3 use B2@.115 SF .98 3.96 4.94
  5 use B2@.115 SF .77 3.96 4.73
Add for keyway beveled on two edges, one use. No stripping included [view picture]
  2" x 4" B2@.027 LF .42 .93 1.35
  2" x 6" B2@.027 LF .65 .93 1.58
Driveway and walkway edge forms Material costs include stakes, nails, and form oil and 5% waste. Per LF of edge form. When forms are required on both sides of the concrete, include the length of each side plus the end widths.
2" x 4" edge form
  Using 2" x 4" lumber, .7 BF per LF — MBF 605.00 — 605.00
  Using nails, ties and form oil, per LF — LF .22 — .22
  1 use B2@.050 LF .58 1.72 2.30
  3 use B2@.050 LF .35 1.72 2.07
  5 use B2@.050 LF .30 1.72 2.02
2" x 6" edge form
  Using 2" x 6" lumber, 1.05 BF per LF — MBF 617.00 — 617.00
  1 use B2@.050 LF .81 1.72 2.53
  3 use B2@.050 LF .45 1.72 2.17
  5 use B2@.050 LF .37 1.72 2.09
2" x 8" edge form
  Using 2" x 8" lumber, 1.4 BF per LF — MBF 598.00 — 598.00
  1 use B2@.055 LF 1.04 1.90 2.94
  3 use B2@.055 LF .56 1.90 2.46
  5 use B2@.055 LF .45 1.90 2.35
2" x 10" edge form
  Using 2" x 10" lumber, 1.75 BF per LF — MBF 630.00 — 630.00
  1 use B2@.055 LF 1.26 1.90 3.16
  3 use B2@.055 LF .66 1.90 2.56
  5 use B2@.055 LF .52 1.90 2.42
2" x 12" edge form
  Using 2" x 12" lumber, 2.1 BF per LF — MBF 707.00 — 707.00
  1 use B2@.055 LF 1.64 1.90 3.54
  3 use B2@.055 LF .83 1.90 2.73
  5 use B2@.055 LF .65 1.90 2.55
Plywood forming For foundation walls, building walls and retaining walls, using 3/4" plyform with 10% waste and 2" bracing with 20% waste. All material costs include nails, ties, clamps, form oil and stripping. Costs shown are per SF of contact area. When forms are required on both sides of the concrete, include the contact surface area for each side.
  Using 3/4" plyform, per MSF — MSF 1,250.00 — 1,250.00
  Using 2" bracing, per MBF — MBF 611.00 — 611.00
  Using nails, ties, clamps & form oil, per SF — SFCA .22 — .22

The figures above are from a time and money saving construction cost manuals from Craftsman Book Company. Over 50 cost estimating databases are available and all come with the popular National Estimator program.

National Estimator helps you compile estimates and bids for any construction project

National Estimator lets you use these costs to create estimates for new construction, repair and remodeling, commercial and industrial projects. Copy and paste and anything you see here into your estimate. Then add overhead and profit and print the bid – or turn your bid into an invoice that goes out in a window envelope. It’s quick, easy and flexible.

Find out more about using these cost estimates with the National Estimator program:

Click here for more information on getting these cost estimates in book form and CD-ROM

Click here for more information on getting these costs as a download on the Web.

National Estimator Includes the following features:
Prints estimates and saves estimates to disk.
Add any percent for overhead, profit and sales tax. Plus, show or hide markup and unit costs.
Change, copy, revise or delete an estimate at any time.
Use your own labor rates and man-hour estimates.
Export to Excel, Word, QuickBooks Pro and others
Organize estimates by division with subtotals.
Turn estimates into invoices
No need to be connected to the Web when estimating.
Includes an extensive help system and free phone support.
CD-ROM includes the Watch Me video on disk.

www.contractors-license.org