02 Existing Conditions (cont.)
    6" concrete with rebars (1 CY of waste per 38 SF demolished) C3@.089 SF — 4.21 2.77 6.98
    8" concrete with mesh but no rebars (1 CY of waste per 32 SF demolished) C3@.109 SF — 5.15 3.40 8.55
    8" concrete with rebars (1 CY of waste per 27 SF demolished) C3@.125 SF — 5.91 3.90 9.81
Concrete over 8" to 12" thick
    Per CY without rebars (2 CY of waste per 1 CY demolished) C3@4.60 CY — 217.00 143.00 360.00
    Per CY with rebars (2.4 CY of waste per 1 CY demolished) C3@5.29 CY — 250.00 165.00 415.00
Demolish concrete curb
    Curb and 24" monolithic gutter (7 LF per CY) C3@.100 LF — 4.73 3.12 7.85
    Planter and batter type curbs, 6" wide (30 LF per CY) C3@.043 LF — 2.03 1.34 3.37
Remove pavement markings by water blasting. Use $100.00 as a minimum charge
      Water blaster, per hour — Hour — — 12.30 13.20
      4" wide strips CL@.032 LF — 1.29 .39 1.68
      Per square foot CL@.098 SF — 3.96 1.20 5.16
Fencing demolition Equipment includes one 5 CY dump truck. No salvage except as noted. These costs include loading and hauling to a legal dump within 6 miles. Dump fees are not included. See Waste Disposal. Use $250.00 as a minimum charge.
Remove chain link fence, To 4' high C4@.030 LF — 1.26 .42 1.68
  5' to 8' high C4@.055 LF — 2.31 .78 3.09
Remove and salvage chain link fence, To 8' high C4@.073 LF — 3.07 1.03 4.10
Remove and dispose wood fence
  Picket or board fence to 4' high C4@.056 LF — 2.35 .79 3.14
  Picket or board fence 5' to 8' high C4@.080 LF — 3.36 1.13 4.49
  Split rail fence, 2 or 3 rail C4@.035 LF — 1.47 .50 1.97
Remove and dispose wood or chain link fence gate To 8' high, including one gate post C4@.333 LF — 14.00 4.71 18.71
  
Highway-type guardrail demolition These costs include loading and hauling to a legal dump within 6 miles. Dump fees are not included. See Waste Disposal. No salvage except as noted. Equipment includes one wheel-mounted air compressor, one paving breaker and jackhammer bits, one 55 HP wheel loader with integral backhoe and one 5 CY dump truck. Use $500.00 as a minimum charge.
  Remove and dispose guardrail C4@.043 LF — 1.81 1.34 3.15
  Remove guardrail in salvage condition C4@.074 LF — 3.11 2.31 5.42
  Remove and dispose guardrail posts C3@.245 Ea — 11.60 7.63 19.23
Manhole, Piping and Underground Tank Demolition No salvage of materials except as noted. These costs include loading and hauling to a legal dump within 6 miles. Dump fees are not included. See Waste Disposal. Equipment includes one wheel-mounted air compressor, one paving breaker and jackhammer bits, one 55 HP wheel loader with integral backhoe and one 5 CY dump truck. Use $400.00 as a minimum charge.
Manholes and catch basins, demolition, to 10' deep. Break below collar and plug
    Brick C3@5.16 Ea — 244.00 161.00 405.00
    Masonry C3@5.33 Ea — 252.00 166.00 418.00

The figures above are from a time and money saving construction cost manuals from Craftsman Book Company. Over 50 cost estimating databases are available and all come with the popular National Estimator program.

National Estimator helps you compile estimates and bids for any construction project

National Estimator lets you use these costs to create estimates for new construction, repair and remodeling, commercial and industrial projects. Copy and paste and anything you see here into your estimate. Then add overhead and profit and print the bid – or turn your bid into an invoice that goes out in a window envelope. It’s quick, easy and flexible.

Find out more about using these cost estimates with the National Estimator program:

Click here for more information on getting these cost estimates in book form and CD-ROM

Click here for more information on getting these costs as a download on the Web.

National Estimator Includes the following features:
Prints estimates and saves estimates to disk.
Add any percent for overhead, profit and sales tax. Plus, show or hide markup and unit costs.
Change, copy, revise or delete an estimate at any time.
Use your own labor rates and man-hour estimates.
Export to Excel, Word, QuickBooks Pro and others
Organize estimates by division with subtotals.
Turn estimates into invoices
No need to be connected to the Web when estimating.
Includes an extensive help system and free phone support.
CD-ROM includes the Watch Me video on disk.

www.contractors-license.org