Concrete Slab Sawing, Subcontract (cont.) Using a gasoline powered saw. Costs per linear foot for cured concrete assuming a level surface with good access and saw cut lines laid out and pre-marked by others. Costs include local travel time. Minimum cost will be $250. Electric powered slab sawing will be approximately 40% higher for the same depth.
Green concrete (2 days old) sawing will usually cost 15 to 20% less. Work done on an hourly basis will cost $125 per hour for slabs up to 4" thick and $135 per hour for 5" or 6" thick slabs. A two hour minimum charge will apply on work done on an hourly basis.
Asphalt Sawing, Subcontract Using a gasoline powered saw. Minimum cost will be $200. Cost per linear foot of green or cured asphalt, assuming level surface with good access and saw cut lines laid out and pre-marked by others. Costs include local travel time. Work done on an hourly basis will cost $115 per hour for asphalt up to 4" thick and $125 per hour for 5" or 6" thick asphalt. A two hour minimum charge will apply on work done on an hourly basis.
  1" or 1-1/2" deep LF .44 .35
  2" deep LF .71 .52
  2-1/2" deep LF .86 .71
  3" deep LF 1.05 .80
  3-1/2" deep LF 1.22 .96
  4" deep LF 1.38 1.05
  5" deep LF 1.74 1.30
  6" deep LF 2.09 1.56
04 Masonry
Craft@Hrs Unit Material Labor Total
Hand cleaning masonry
Brushing (hand cleaning) masonry includes the cost of detergent or chemical solution.
  Light cleanup (100 SF per manhour) M1@.010 SF .03 .47 .50
  Medium scrub (75 SF per manhour) M1@.013 SF .04 .61 .65
  Heavy (50 SF per manhour) M1@.020 SF .06 .94 1.00
04 Masonry (cont.)
Craft@Hrs Unit Material Labor Equipment Total
Water blasting masonry, using rented 400 to 700 PSI power washer with 3 to 8 gallon per minute flow rate, includes blaster rental at $65 per day
  Smooth face (250 SF per manhour) M1@.004 SF — .19 .03 .22
  Rough face (200 SF per manhour) M1@.005 SF — .23 .03 .26
Sandblasting masonry, using 150 PSI compressor (with accessories and sand) at $130.00 per day
  Smooth face (50 SF per manhour) M1@.020 SF .35 .94 .22 1.51
  Rough face (40 SF per manhour) M1@.025 SF .40 1.17 .51 2.08
Steam cleaning masonry, using rented steam cleaning rig (with accessories) at $112.00 per day
  Smooth face (75 SF per manhour) M1@.013 SF — .61 .14 .75
  Rough face (55 SF per manhour) M1@.018 SF — .84 .19 1.03
04 Masonry (cont.)
Craft@Hrs Unit Material Labor Total
Repointing brick, cut out joint, mask (blend-in), and regrout (tuck pointing)
  30 SF per manhour M1@.033 SF .08 1.55 1.63
Add for masking adjacent surfaces — % — 5.0 —
Add for difficult stain removal — % 50.0 50.0 —
Add for working from scaffold — % — 20.0 —

The figures above are from a time and money saving construction cost manuals from Craftsman Book Company. Over 50 cost estimating databases are available and all come with the popular National Estimator program.

National Estimator helps you compile estimates and bids for any construction project

National Estimator lets you use these costs to create estimates for new construction, repair and remodeling, commercial and industrial projects. Copy and paste and anything you see here into your estimate. Then add overhead and profit and print the bid – or turn your bid into an invoice that goes out in a window envelope. It’s quick, easy and flexible.

Find out more about using these cost estimates with the National Estimator program:

Click here for more information on getting these cost estimates in book form and CD-ROM

Click here for more information on getting these costs as a download on the Web.

National Estimator Includes the following features:
Prints estimates and saves estimates to disk.
Add any percent for overhead, profit and sales tax. Plus, show or hide markup and unit costs.
Change, copy, revise or delete an estimate at any time.
Use your own labor rates and man-hour estimates.
Export to Excel, Word, QuickBooks Pro and others
Organize estimates by division with subtotals.
Turn estimates into invoices
No need to be connected to the Web when estimating.
Includes an extensive help system and free phone support.
CD-ROM includes the Watch Me video on disk.