Non-Reinforced Concrete Pipe (cont.) Smooth wall, standard strength, with tongue-and-groove mortar joint ends. Installed in an open trench. Equipment includes a wheel-mounted 1 CY backhoe for lifting and placing the pipe. Trench excavation, bedding material and backfill are not included. Use $3,500 as a minimum job charge.
  15" pipe C5@.210 LF 16.10 9.57 2.49 28.16
  18" pipe C5@.234 LF 22.00 10.70 2.77 35.47
  21" pipe C5@.234 LF 25.50 10.70 2.77 38.97
  24" pipe C5@.260 LF 31.80 11.80 3.08 46.68
  30" pipe C5@.286 LF 52.20 13.00 3.39 68.59
Non-Reinforced Perforated Concrete Underdrain Pipe Perforated smooth wall, standard strength, 3' lengths with tongue and groove mortar joint ends. Installed in an open trench. Equipment includes a wheel-mounted 1 CY backhoe for lifting and placing the pipe. Trench excavation, bedding material and backfill are not included. Use $2,200 as a minimum job charge.
      6" pipe C5@.152 LF 5.96 6.93 1.80 14.69
      8" pipe C5@.208 LF 8.05 9.48 2.46 19.99
Reinforced Concrete Pipe Class III, 1350 “D”-load, ASTM C-76, 8' lengths. Tongue-and-groove mortar joint ends. Installed in an open trench. Equipment cost shown is for a wheel-mounted 1 CY backhoe for lifting and placing the pipe. Trench excavation, dewatering, backfill and compaction are not included. Use $3,000 as a minimum job charge.
  18" pipe C5@.272 LF 24.80 12.40 3.22 40.42
  24" pipe C5@.365 LF 36.00 16.60 4.33 56.93
  30" pipe C5@.426 LF 56.40 19.40 5.05 80.85
  36" pipe C5@.511 LF 81.40 22.90 6.06 110.36
  42" pipe C5@.567 LF 110.00 25.80 6.72 142.52
  48" pipe C5@.623 LF 141.00 28.40 7.38 176.78
  54" pipe C5@.707 LF 176.00 32.20 8.38 216.58
  60" pipe C5@.785 LF 208.00 35.80 9.30 253.10
  66" pipe C5@.914 LF 258.00 41.60 10.80 310.40
  72" pipe C5@.914 LF 339.00 41.60 10.80 391.40
  78" pipe C5@.914 LF 485.00 41.60 10.80 537.40
  84" pipe C5@1.04 LF 545.00 47.40 12.30 604.70
  90" pipe C5@1.04 LF 646.00 47.40 12.30 705.70
  96" pipe C5@1.18 LF 714.00 53.80 14.00 781.80
Reinforced Elliptical Concrete Pipe Class III, 1350 “D”, C-502-72, 8' lengths, tongue-and-groove mortar joint ends. Installed in an open trench. Equipment includes a wheel-mounted 1 CY backhoe for lifting and placing the pipe. Trench excavation, dewatering, backfill and compaction are not included. Use $3,500 as a minimum job charge.
  19" x 30" pipe, 24" pipe equivalent C5@.356 LF 84.80 16.20 4.22 105.22
  24" x 38" pipe, 30" pipe equivalent C5@.424 LF 88.20 19.30 5.02 112.52
  29" x 45" pipe, 36" pipe equivalent C5@.516 LF 106.00 23.50 6.11 135.61
  34" x 53" pipe, 42" pipe equivalent C5@.581 LF 138.00 26.50 6.88 171.38
  38" x 60" pipe, 48" pipe equivalent C5@.637 LF 175.00 29.00 7.55 211.55
  48" x 76" pipe, 60" pipe equivalent C5@.797 LF 248.00 36.30 9.44 293.74
  53" x 83" pipe, 66" pipe equivalent C5@.923 LF 295.00 42.10 10.90 348.00
  58" x 91" pipe, 72" pipe equivalent C5@.923 LF 342.00 42.10 10.90 395.00
Flared Concrete End Sections For round concrete drain pipe, precast. Equipment includes a wheel-mounted1 CY backhoe for lifting and placing the items. Trench excavation, dewatering, backfill and compaction are not included. Use $2,500 as a minimum job charge.
  12" opening, 530 lbs C5@2.41 Ea 318.00 110.00 28.60 456.60
  15" opening, 740 lbs C5@2.57 Ea 345.00 117.00 30.50 492.50
  18" opening, 990 lbs C5@3.45 Ea 405.00 157.00 40.90 602.90
  24" opening, 1,520 lbs C5@3.45 Ea 447.00 157.00 40.90 644.90
  30" opening, 2,190 lbs C5@3.96 Ea 529.00 180.00 46.90 755.90
  36" opening, 4,100 lbs C5@3.96 Ea 927.00 180.00 46.90 1,153.90
  42" opening, 5,380 lbs C5@4.80 Ea 1,130.00 219.00 56.90 1,405.90
  48" opening, 6,550 lbs C5@5.75 Ea 1,460.00 262.00 68.40 1,790.40
  54" opening, 8,000 lbs C5@7.10 Ea 2,420.00 323.00 84.10 2,827.10

The figures above are from a time and money saving construction cost manuals from Craftsman Book Company. Over 50 cost estimating databases are available and all come with the popular National Estimator program.

National Estimator helps you compile estimates and bids for any construction project

National Estimator lets you use these costs to create estimates for new construction, repair and remodeling, commercial and industrial projects. Copy and paste and anything you see here into your estimate. Then add overhead and profit and print the bid – or turn your bid into an invoice that goes out in a window envelope. It’s quick, easy and flexible.

Find out more about using these cost estimates with the National Estimator program:

Click here for more information on getting these cost estimates in book form and CD-ROM

Click here for more information on getting these costs as a download on the Web.

National Estimator Includes the following features:
Prints estimates and saves estimates to disk.
Add any percent for overhead, profit and sales tax. Plus, show or hide markup and unit costs.
Change, copy, revise or delete an estimate at any time.
Use your own labor rates and man-hour estimates.
Export to Excel, Word, QuickBooks Pro and others
Organize estimates by division with subtotals.
Turn estimates into invoices
No need to be connected to the Web when estimating.
Includes an extensive help system and free phone support.
CD-ROM includes the Watch Me video on disk.

www.contractors-license.org