8" regular block, standard brick, 8-man crew, cavity wall assemblies using scaffolding (cont.) Typical costs for smooth red clay brick and regular-weight concrete block, each one wythe wide. Both walls are laid up with a running bond with 3/8" horizontal and vertical joints. These costs include the bricks, block, mortar, wall ties and normal waste. Foundations and horizontal reinforcing in the block are not included. See wall foundation costs in the section Concrete Spread Footings. "Wythe" means the quantity of bricks in the thickness of the wall. Labor costs increase with increases in wall height. Equipment costs include scaffolding. Equipment rental costs are based on the production rate of an 8-man crew. For reinforcing costs, see the section on vertical cell grout.
17'- 4" high wall [view picture]
        Cost per square foot B9@.415 SF 8.79 13.48 .06 22.33
        Cost per block B9@.168 Ea 7.81 5.45 .03 13.29
        Cost per linear foot of wall B9@7.20 LF 193.06 233.85 1.13 428.03
18'- 0" high wall
        Cost per square foot B9@.424 SF 8.79 13.77 .07 22.62
        Cost per block B9@.173 Ea 7.81 5.62 .03 13.46
        Cost per linear foot of wall B9@7.64 LF 200.95 247.94 1.19 450.09
18'- 8" high wall
        Cost per square foot B9@.432 SF 8.79 14.03 .07 22.88
        Cost per block B9@.175 Ea 7.81 5.68 .03 13.52
        Cost per linear foot of wall B9@8.07 LF 208.85 261.90 1.26 472.01
19'- 4" high wall
        Cost per square foot B9@.439 SF 8.79 14.25 .07 23.11
        Cost per block B9@.178 Ea 7.81 5.78 .03 13.62
        Cost per linear foot of wall B9@8.50 LF 216.74 276.03 1.33 494.10
20'- 0" high wall
        Cost per square foot B9@.447 SF 8.79 14.51 .07 23.37
        Cost per block B9@.182 Ea 7.81 5.91 .03 13.75
        Cost per linear foot of wall B9@8.94 LF 224.64 290.15 1.40 516.18
12" regular block, standard brick, 8-man crew, cavity wall assemblies using scaffolding Typical costs for smooth red clay brick and regular-weight concrete block, each one wythe wide. Both walls are laid up with a running bond with 3/8" horizontal and vertical joints. These costs include the bricks, block, mortar, wall ties and normal waste. Foundations and horizontal reinforcing in the block are not included. See wall foundation costs in the section Concrete Spread Footings. "Wythe" means the quantity of bricks in the thickness of the wall. Labor costs increase with increases in wall height. Equipment costs include scaffolding. Equipment rental costs are based on the production rate of an 8-man crew. For reinforcing costs, see the section on vertical cell grout.
2'- 0" high wall
        Cost per square foot B9@.308 SF 10.35 10.00 — 20.35
        Cost per block B9@.141 Ea 9.20 4.58 — 13.78
        Cost per linear foot of wall B9@.617 LF 14.59 20.03 — 34.62
2'- 8" high wall
        Cost per square foot B9@.308 SF 10.35 10.00 — 20.35
        Cost per block B9@.141 Ea 9.20 4.58 — 13.78
        Cost per linear foot of wall B9@.824 LF 23.52 26.76 — 50.28
3'- 4" high wall
        Cost per square foot B9@.308 SF 10.35 10.00 — 20.35
        Cost per block B9@.141 Ea 9.20 4.58 — 13.78
        Cost per linear foot of wall B9@1.03 LF 32.45 33.48 — 65.93

The figures above are from a time and money saving construction cost manuals from Craftsman Book Company. Over 50 cost estimating databases are available and all come with the popular National Estimator program.

National Estimator helps you compile estimates and bids for any construction project

National Estimator lets you use these costs to create estimates for new construction, repair and remodeling, commercial and industrial projects. Copy and paste and anything you see here into your estimate. Then add overhead and profit and print the bid – or turn your bid into an invoice that goes out in a window envelope. It’s quick, easy and flexible.

Find out more about using these cost estimates with the National Estimator program:

Click here for more information on getting these cost estimates in book form and CD-ROM

Click here for more information on getting these costs as a download on the Web.

National Estimator Includes the following features:
Prints estimates and saves estimates to disk.
Add any percent for overhead, profit and sales tax. Plus, show or hide markup and unit costs.
Change, copy, revise or delete an estimate at any time.
Use your own labor rates and man-hour estimates.
Export to Excel, Word, QuickBooks Pro and others
Organize estimates by division with subtotals.
Turn estimates into invoices
No need to be connected to the Web when estimating.
Includes an extensive help system and free phone support.
CD-ROM includes the Watch Me video on disk.

www.contractors-license.org